Victoria · SOPA 2002

SOPA Deadline Calculator VIC

Calculate your payment claim deadlines in Victoria under the Building and Construction Industry Security of Payment Act 2002. Warning: VIC adjudication window is only 10 business days from receiving the payment schedule — shorter than NSW. Act quickly.

VIC SOPA Deadline Calculator

Building and Construction Industry Security of Payment Act 2002 (VIC) · Victoria public holidays included

Victoria — SOPA 2002
Payment schedule: 10 business days · Payment due: 15 business days from reference date · Adjudication: 10 business days from schedule (or 20 BD from payment due date if no schedule served)
Adjudication body: Victorian Building Authority (VBA)

The date the respondent received your VIC payment claim.

VIC SOPA — Key Deadlines at a Glance

Under the Building and Construction Industry Security of Payment Act 2002 (VIC), the most important difference from NSW is the adjudication window: only 10 business days from receiving a payment schedule. This is half the NSW window — Victorian subcontractors must act quickly.

Payment Schedule: 10 business days from receiving your payment claim.

Payment Due Date: 15 business days from the reference date (maximum 30 business days by contract).

Adjudication: 10 business days from receiving the payment schedule (if for less than claimed), or 20 business days from payment due date if no schedule was served.

VIC SOPA — Frequently Asked Questions