Tasmania · SOPA 2009

SOPA Deadline Calculator TAS

Calculate your payment claim deadlines in Tasmania under the Building and Construction Industry Security of Payment Act 2009. Payment schedule: 10 business days. Adjudication window: 20 business days. TAS public holidays (including Eight Hours Day) included.

TAS SOPA Deadline Calculator

Building and Construction Industry Security of Payment Act 2009 (TAS) · Tasmania public holidays included

Tasmania — SOPA 2009
Payment schedule: 10 business days · Payment due: 15 business days from reference date · Adjudication: 20 business days from schedule (or 10 BD from payment due date if no schedule)
Adjudication body: Consumer, Building and Occupational Services (CBOS)

TAS SOPA — Frequently Asked Questions