South Australia · SOPA 2009
Calculate your payment claim deadlines in South Australia under the Building and Construction Industry Security of Payment Act 2009. Payment schedule: 15 business days. SA public holidays (including Adelaide Cup) included.
Building and Construction Industry Security of Payment Act 2009 (SA) · SA public holidays included
South Australia — SOPA 2009
Payment schedule: 15 business days · Payment due: 15 business days from reference date · Adjudication: 10 business days from schedule (or 20 BD from payment due date if no schedule)
Adjudication body: Consumer and Business Services SA (CBS)
For complex SA SOPA disputes, a specialist South Australian construction lawyer can advise on your rights and the CBS adjudication process.